Meyar
العربية
Back to Property

Prototype / Modelled evidence

Warehouse 086

MEYAR-RYD-0086 · Al Sulimaniyah

Base. Scenario and session assumptions update this selected asset only.

Decision Summary

21.6%

HBU option: logistics · Base

Risk: Moderate · 29/100Confidence: Medium · 76%

Project Definition

HBU option
logistics
Land area
6,801 m²
Gross floor area (GFA)
39,038 m²
Gross leasable area (GLA)
33,900 m²
Units
52

Baseline

Cost Assumptions

Acquisition / land
SAR 111,513,000
Hard construction cost
SAR 17,522,000
Soft costs
SAR 2,103,000
Financing
SAR 5,566,000
Contingency
SAR 1,374,000

Total project cost = land + hard cost + soft cost + contingency + financing. Development margin = profit / revenue; return on cost = profit / total project cost.

Revenue Assumptions

Expected revenue
SAR 176,232,000
Sales price
Baseline
Occupancy
91.4%
Exit / terminal value
SAR 176,232,000

Timeline

  1. 1AcquisitionSept 2026Oct 2026 · 1 monthDelays the entire programme and financing drawdown.
  2. 2DesignOct 2026Feb 2027 · 4 monthsPushes approvals and contractor mobilisation.
  3. 3ApprovalsDec 2026May 2027 · 5 monthsDefers construction start and increases holding cost.
  4. 4ConstructionMay 2027Mar 2028 · 10 monthsRaises financing cost and postpones revenue.
  5. 5CommercialisationNov 2027May 2028 · 6 monthsSlows collections and extends payback.
  6. 6ExitSept 2028Oct 2028 · 1 monthDefers terminal proceeds and reduces present value.

Delivery delay: 0 months

Financial Results

Total project cost
SAR 138,078,000
Expected revenue
SAR 176,232,000
Gross profit
SAR 38,154,000
Net profit
SAR 38,154,000
Development margin
21.6%
Internal rate of return (IRR)
14.6%
Net present value (NPV)
SAR 11,512,000
ROI
27.6%
Equity requirement
SAR 55,231,000
Debt funding
SAR 82,847,000
Payback
24 months
Break-even
SAR 138,078,000