Value
Off Plan- Approved Baseline
- SAR 104,141,000
- Prototype Actual
- SAR 98,933,950
- Variance
- -SAR 5,207,050
- Relative variance
- -5.0%
value uses higher-positive; material at 5% and critical at 12%. · Materiality: Material
value uses higher-positive; material at 5% and critical at 12%. · Materiality: Material
Comparison unavailable because an applicable baseline or prototype actual is missing. · Materiality: Unavailable
developmentCost uses higher-negative; material at 6% and critical at 15%. · Materiality: Critical
revenue uses higher-positive; material at 6% and critical at 15%. · Materiality: Minor
noi uses higher-positive; material at 5% and critical at 12%. · Materiality: Minor
occupancy uses higher-positive; material at 4% and critical at 10%. · Materiality: Minor
schedule uses higher-negative; material at 10% and critical at 25%. · Materiality: Critical
risk uses higher-negative; material at 10% and critical at 25%. · Materiality: Material
returnIndicator uses higher-positive; material at 8% and critical at 18%. · Materiality: Material
Local deterministic explanation; no external model or autonomous execution.